Bridge Girder and Steel Structure Transport in Vietnam: Vehicles, Lashing and Process
Bridge girder transport means moving concrete or steel girders from the casting yard or fabrication shop to the construction site safely and in installation order. Three things decide success: choosing vehicles that match the length and weight, supporting and lashing at the right points, and getting a road permit when limits are exceeded.
This article is for contractors, girder casting yards and project owners who need a transport plan. The detailed legal requirements are covered in two separate H-Cargo articles linked below.

Table of contents:
I. How is bridge girder transport different from steel structures and precast elements?
The difference is how each type gets damaged: prestressed concrete girders are vulnerable to cracking and tipping, steel structures to bending and paint damage, and small precast elements mainly to chipped edges and corners. So although they are all long and heavy, the support points, lashing and suitable vehicles differ.
Element type | Transport characteristics | Main risks | Public example |
Super T and prestressed concrete I-girders | Very long, heavy, high centre of gravity (I-girders) | Cracking from wrong support points, tipping in bends | — |
Box girders, elevated bridge deck segments | Heavy and wide, usually moved at night with escort | Overloading bridges and culverts on the route | Hanoi Ring Road 3 elevated bridge segments: carried 42 km from Vinh Phuc, about 2.5 hours per trip, tractors of over 100 tonnes, escorted by traffic inspectors (VTC News, VnExpress, 04/2020) |
Steel structures (trusses, columns, steel beams, rails) | Long but light, often over-length before overweight | Bending, paint damage, shifting under braking | — |
Precast elements (box culverts, piles, panels) | Large quantities, moderate size | Chipped edges and corners; incorrect stacking | — |
Why do light steel structures often need a permit?
Because the oversize threshold is based on the dimensions of the whole vehicle-and-cargo combination, not on weight. For example, a steel rail or beam weighing only a few tonnes still needs a road permit if loading it makes the combination longer than 20 m.
II. When does bridge girder transport need a road permit?
A permit is needed when the vehicle-and-cargo combination exceeds any one of the oversize or overweight thresholds for length, width, height or total weight. Under Article 10 of Circular 12/2025/TT-BXD, the thresholds are: longer than 20 m, wider than 2.5 m, higher than 4.2 m (4.35 m for container vehicles), or a total weight above 48 tonnes.
For bridge girders, almost every shipment exceeds the length threshold. Three points to know:
Current regulation: Circular 12/2025/TT-BXD (effective 01/07/2025), amended by Circular 19/2026/TT-BXD (effective 01/07/2026), consolidated in Consolidated Document 26/VBHN-BXD dated 02/06/2026.
Issuing authority: the provincial Department of Construction, as guided by Official Letter 3942/CĐBVN-TCGT dated 12/08/2025 of the Vietnam Road Administration.
QR code on permits: applies from 01/01/2027 under Circular 19/2026/TT-BXD.
For documents, timelines and common mistakes, H-Cargo has a separate article on the Vietnam road permit for oversize and overweight vehicles. The latest legal changes are covered in Vietnam oversize and overweight cargo regulations.
Related articles:
- Transformer transportation for power projects
- Vietnam oversize and overweight cargo regulations (latest)III. Which vehicles should be used for bridge girder transport?
Choose the vehicle by length first, then weight, then route conditions. Long girders need extendable trailers or tractor-trailer combinations that can be extended. Heavy girders need multi-axle trailers to spread the load. If the route has weak bridges or the casting yard is next to a river, consider a barge.
Vehicle | Suitable for | Selection notes |
Flatbed semi-trailer | Medium-length steel structures and precast elements | Cheap and flexible; easily over-length when cargo overhangs the rear |
Extendable trailer | I-girders, steel beams, long rails | Deck length adjusts to the cargo; still needs a permit when the combination exceeds 20 m |
Low-bed trailer | Tall elements that need a lower combined height | Reduces the risk of exceeding 4.2 m; low clearance, struggles on rough roads |
Multi-axle or hydraulic modular trailer | Super T girders, box girders, heavy deck segments | Spreads the load over many axles, self-levelling; bridges and culverts must be surveyed carefully |
Barge | Casting yards or sites near rivers and ports | Avoids weak road bridges; needs landing points and cranes at both ends |

Have girders or steel structures to move? Send H-Cargo the drawings and locations, and our project team will propose vehicles and a route plan. Get a quote
Do Super T girders always require hydraulic trailers?
No. The vehicle depends on the length and weight of each girder and the allowable load of bridges and culverts on the route. The final plan is prepared by the carrier based on the route survey and must match the parameters in the road permit.
IV. How should bridge girders be supported and lashed?
The principle is to support the girder at the points specified by the designer or manufacturer, prevent sideways tipping, and never let lashing cables bear directly on concrete or paint. Wrong support points can load a prestressed girder against its design direction and cause cracks. This kind of damage often only appears at acceptance.
Loading checklist:
Support points: follow the drawings or the casting yard's instructions; use timber or rubber bearings, never support directly on the steel deck.
Anti-tipping: I-girders and girders with a high centre of gravity need bracing or anti-tipping frames on both sides.
Lashing: cables or turnbuckles with corner protectors; re-check tension after the first stretch of road.
Steel structures: support at multiple points to prevent sagging, pad to protect paint, and block against sliding under braking.
Marking: flashing lights and warning flags at the furthest overhang, as required by the permit.
Road risks remain, so the shipper should also consider project cargo insurance before the move.

V. What are the steps from casting yard to construction site?
The process has 6 steps: route survey, transport plan, road permit, loading, escorted transport, and unloading in installation order.
Route survey: measure clearances, turning radii, bridge and culvert capacity, and power lines from the casting yard to the site. In practice, permit applications usually include a route survey report for oversize and overweight cargo prepared by a consultant.
Transport plan: choose vehicles, loading layout, support points and schedule (usually at night, avoiding peak hours).
Road permit: apply to the provincial Department of Construction based on the vehicle-and-cargo parameters.
Loading at the casting yard or shop: lift at the girder's built-in lifting points and support and lash according to the checklist.
Transport: follow the permitted route and hours; use escort or pilot vehicles when the permit requires them.
Unloading at site: place in the right position and order so the erection team can work immediately, avoiding a second lift.
Why is delivery order as important as speed?
Because construction sites rarely have room to store girders. For example, on the Ring Road 3 elevated bridge project, the contractor had to install 563 girder segments for 52 spans. The girders were delivered at night under traffic inspector escort, then lifted and placed onto the bearings (VnExpress, 29/04/2020). Delivering out of order means the erection team waits or the cargo has to be shuffled.
VI. What information should you prepare to get a girder transport plan quickly?
Send the 5 groups of information below so the carrier can survey and quote without repeated questions:
Element drawings: length × width × height, weight of each girder, lifting and support points.
Quantity and schedule: total girders, girders per night, erection start date.
Locations: casting yard or shop (origin), site (destination), site access road.
Handling conditions: who provides cranes at each end and their lifting capacity.
Other requirements: insurance, acceptance, permitted driving hours required by the project owner.
H-Cargo's project cargo transport service plans moves from route survey to unloading at the site. For oversized cargo in special containers, see our OOG service.
VII. FAQs about bridge girder transport
How long can a girder be before it needs a road permit?
It is based on the whole vehicle-and-cargo combination, not the girder alone. A combination longer than 20 m, wider than 2.5 m, higher than 4.2 m or heavier than 48 tonnes in total is oversize or overweight cargo and needs a road permit (Article 10, Circular 12/2025/TT-BXD).
Do light steel structures need a permit?
Yes, if the combination exceeds the dimension limits. The oversize threshold is based on the dimensions of the vehicle-and-cargo combination, so light but long steel still needs a permit when the combination is longer than 20 m.
Can bridge girders be transported by barge?
Yes, when the casting yard or site is near a river or port. Barges avoid weak road bridges, but you need landing points and cranes at both ends, plus a short road leg to the installation point.
Who is responsible if a girder cracks during transport?
It depends on the transport contract, the condition report signed before loading and the approved support and lashing plan. Take photos and record the girder's condition on receipt, and insure high-value shipments with project cargo insurance.
VIII. Conclusion
Moving bridge girders, steel structures or precast elements is not hard on the road itself. The hard part is preparation: choosing vehicles by length and weight, supporting and lashing at the right points, getting a permit with the right parameters, and delivering in installation order. A thorough route survey avoids the biggest extra costs: cracked girders, vehicles stopped mid-route and a site waiting for cargo.
Author: Navy Ngo - Project team
Contact us for a free consultation:
H-Cargo International Logistics
113-115 Ung Van Khiem St., Ward Thanh My Tay, Ho Chi Minh City
Tel: +84 888 909 186
Email: project@hcargovn.com
Web: www.hcargovn.com
Sources cited in this article: Circular 12/2025/TT-BXD, amended by Circular 19/2026/TT-BXD (Consolidated Document 26/VBHN-BXD); Official Letter 3942/CĐBVN-TCGT of the Vietnam Road Administration; VnExpress, VTC News (29/04/2020). Accessed 17/11/2026. For reference only; check that regulations are still in force at the time of application.